Consumers Co-operative Refineries Ltd. Control Operations Centre

Bird constructed a 16,000 square foot control room on a structural slab foundation with precast walls and double-tee roof, structural steel studs and masonry partitions.

Client
Consumers Co-operative Refineries LTD.
Consultant
LAG Global Projects ULC & Stantec Inc.
Contract Type
Stipulated Sum
Project Size
16,400 sq. ft.
Duration
24 Months
Project Value
$9,250,000

Located within the blast zone of an active plant, Bird used precast panels measuring 14.5 inches thick. To assemble the building the main access to the plant was shutdown and a secondary access was used to control workflow. Daily meetings ensured coordination was streamlined during the erection of the pre-cast walls and roof. Bird synchronized deliveries of the precast panels and assembled each of the panels at site using a 270-ton crane. The synchronized deliveries allowed Bird to adhere to its schedule while maintaining uninterrupted site operations.