Manitoba Hydro Dorsey Converter Station

Bird provided protection for the 5,000 square foot existing pre-engineered building by constructing a building to encase it. The construction consisted of cast-in-place foundation piles, which were required to support the 190 piece precast concrete structure that was loaded using a 500 ton crane.

Client
MANITOBA HYDRO
Consultant
STANTEC INC.
Contract Type
STIPULATED SUM
Project Size
12,000 SQ. FT.
Duration
18 MONTHS
Project Value
$5,100,000

The location of this project was particularly difficult since the Dorsey converter station is located inside of an operating Manitoba Hydro facility within close proximity to high voltage electrical lines. Bird’s team exercised extensive pre-planning and safety procedures to complete this job successfully and safely.