Enbridge Clipper Expansion
Enbridge Clipper Expansion

Enbridge Clipper Expansion

multiple locations across alberta, saskatchewan & manitoba

CLIENT:Enbridge Pipelines Inc.
CONSULTANT:Jacobs Canada Inc.
CONTRACT TYPE:Stipulated Sum
DURATION:Phase 1: 12 months
Phase 2: 13 months
Enbridge Clipper Expansion

Bird worked with Enbridge to meet their goal to increase the Alberta Clipper Pipeline capacity from 450,000 barrels-per-day to 800,000 barrels-per-day of heavy crude oil through increased pumping horsepower. The Canadian portion of the pipeline is over 1,000 kilometres long, transporting crude oil from the Hardisty terminal in Alberta to the Gretna station in Manitoba.

Bird’s work on Phase 1 included 130 square metre expansions to each of the six existing facilities to house a new mainline pump. The team performed civil works, fabricated and installed piping and electrical systems. Bird overcame challenges of incorporating new systems into existing ones, working in remote locations and building during inclement winter weather — at times the site temperature dropped below minus 63°C. Phase 2 involved the construction of four new pump station facilities including civil works, 13 new pumps and electrical systems at each of the stations.

Upgrades were completed at three pipeline terminals for the Athabasca Pipeline Twinning Project, including mechanical piping, screw piles with pile caps and earthworks. At the peak of construction, more than 40 hydrovac trucks were on-site daily for three to four months to excavate and expose the existing pipelines.

The efforts of Bird’s superintendent for the Alberta Clipper Phase 1 project, Joe Wiegers, has been recognized by Enbridge by presenting him with their major projects safety award for his dedication to maintaining a safe work site. With Joe’s help, Bird successfully achieved zero lost time injuries since the project commenced in the spring 2013.

Enbridge Clipper Expansion
Enbridge Clipper Expansion : Projects : Bird Construction