The team implemented and executed careful coordination of construction activities to avoid disruption to the tenants located directly below during the GoodLife Fitness Centre conversion. However, during construction the team encountered a problem upon removal of the first level ceiling - it was discovered that it was impossible to access the structural steel connections to complete the reinforcement because of existing duct work.

Client
ROSSLAND REAL ESTATE LIMITED
Consultant
PETROFF PARTNERSHIP ARCHITECTS
Contract Type
STIPULATED SUM
Project Size
37,000 SQ. FT.
Duration
4 MONTHS
Project Value
$1,100,000
GoodLife Fitness Centre Tower and partial view of the entrance to the centre

Bird worked with the consultants to re-design the reinforcing requirement, ultimately reducing the requirement for work in the existing tenant space on the first level by 95%. These changes resulted in a more economical plan, significant cost savings and a reduced schedule.