LC Skerry School

LC Skerry School

WAVERLEY, NOVA SCOTIA

CLIENT:DEPARTMENT OF TRANSPORTATION & INFRASTRUCTURE
CONSULTANT:HARVEY ARCHITECTURE
CONTRACT TYPE:DESIGN-BUILD
Project VALUE:$7,300,000
Project SIZE:44,000 SQ. FT.
DURATION:12 MONTHS
LEED CERTIFICATION LEVEL:SILVER
LC Skerry School

The construction of the new LC Skerry School began with the demolition of two existing schools that were built in the mid 1900s. Built into the side of a hill, the new two-storey school employed the use of retaining walls and tilt-up construction methods for the building envelope.

With Bird’s firm schedule and keen organization skills, construction was expedited on time for the upcoming school year. Bird was able to fast-track the schedule by performing the demolition and construction of the new structure concurrently, which required extensive coordination between Bird and its subcontractors.

LC Skerry School : Projects : Bird Construction