MEG Energy Maintenance and Administration Building

MEG Energy Corporation currently has received approval to construct and operate the first two phases of the Christina Lake regional project on 23 of their 80 sections of leased oilsands land. The purpose of phase 2B is to increase the production capacity of the central processing facility to 60,000 barrels of bitumen per day. The phase 2B maintenance building is located immediately adjacent to the existing phase one and two processing facilities.

Client
MEG ENERGY CORPORATION
Consultant
RIDDELL KURCZABA ARCHITECTURE ENGINEERING INTERIOR DESIGN LTD.
Contract Type
STIPULATED SUM
Project Size
28,000 SQ. FT.
Duration
9 MONTHS
Project Value
$10,000,000

Bird constructed the pre-engineered 16,000 square foot maintenance building and provided an expansion to the existing administration building. The expansion includes modification to the existing walkway and the addition of two mudrooms.