Skip to main content
logo-bird-white
Hydro

Muskrat Falls Hydroelectric Generating Station Bulk Excavation And Civil Works

Bird Heavy Civil was the lead in the joint venture, IKC-ONE Earthwork Constructors consortium, which included the participation of the Labrador Innu. The contract included overburden and rock excavation of the intake, powerhouse, spillway, separation wall, switchyard and converter stations and dams at the site of the 824 megawatt hydroelectric generating station in central Labrador.

Client
Nalcor Energy
Consultant
SNC-Lavalin Inc.
Contract Type
Unit Price
Project Size
Over 2.7 million cu. m of earth moved (95,349,600 cu. ft)
Over 1.8 million cu. m of rock blasting and removal (63,566,400 cu. ft)
15,000 cu. m of underwater rock removed (529,720 cu. ft)
Duration
14 months
Project Value
Over $100,000,000

The team worked around-the-clock to complete the project before the winter months with a crew of 400 and 200 pieces of heavy equipment. Almost 300,000 linear metres of rock was drilled with 75- to 165-millimetre holes for blasting. The rock removal commenced at 20 metres above the river level and concluded at 32 metres below water level. In addition, 150,000 cubic metres of earthfill cofferdams and 37,000 cubic metres of roller compacted concrete cofferdams were built.

At the completion of the project, over 2.7 million cubic metres of earth was moved, over 1.8 million cubic metres of rock blasting and removal was completed, and 15,000 cubic metres of underwater rock was removed. With the success of this project, HJO looks forwardto additional contract awards for this ongoing challenging project.