Petro Canada RCP 1.1 Civil Works

The 6,500 cubic yard concrete coker structure was constructed with access only from one end and included a 3,500 cubic yard monolithic base. The base required 350 truck loads of concrete, four pumps and was completed in 14 hours with commendations from the client for its successful execution.

Client
Petro Canada
Consultant
Bantrel Inc.
Contract Type
Stipulated Sum
Project Size
28,000 CU. YD. of concrete
Duration
16 Months
Project Value
$55,000,000
Construction in progress at Petro Canada job site

The elevated portion of the coker went through the winter under heated enclosure in a congested work area. The lack of lay down space required significantly more planning and coordination. An additional elevated structure, the vacuum tower, involved a ring beam atop 12 columns that were over 63 feet high. Bird simultaneously completed the concrete and shallow underground piping work in the nearby sulphur block under separate contract. Bird simultaneously completed the concrete and shallow underground piping work in the nearby sulphur block under separate contract.