Richmond General Hospital Emergency & Diagnostic Imaging

Richmond General Hospital Emergency & Diagnostic Imaging

Richmond, British Columbia

CLIENT:Richmond general hospital
CONSULTANT:stantec architectural
CONTRACT TYPE:stipulated sum
Project VALUE:$2,660,000
DURATION:15 months
Richmond General Hospital Emergency & Diagnostic Imaging

Major structural alteration work had to be coordinated with existing conditions in an operating hospital environment. Dust control, infection control and noise mitigation were major risk issues that were carefully managed. Mechanical and electrical systems were expanded and joined to existing services with no interruption to plant operations. The coordination of work activities involved daily coordination and communications between the hospital staff, the design team and Bird Construction.