Suncor Millennium Naptha Unit & Hydrogen Plant
Suncor Millennium Naptha Unit & Hydrogen Plant
Suncor Millennium Naptha Unit & Hydrogen Plant

Suncor Millennium Naptha Unit & Hydrogen Plant

FORT MCMURRAY, ALBERTA

CLIENT:NORTH AMERICAN ENTERPRISES LTD.
CONSULTANT:BANTREL CO.
CONTRACT TYPE:COST PLUS
Project VALUE:$27,500,000
Project SIZE:9,860 CU. YD. OF CONCRETE
DURATION:16 MONTHS
Suncor Millennium Naptha Unit & Hydrogen Plant

This large scale project required close coordination with other contractors to ensure safety and efficiency. Immediately following the completion of the foundation work, the mechanical contractors were quickly mobilized, setting equipment and erecting steel. Exposure to the harsh northern Alberta winter required the installation of protective hoardings to ensure the project remained on schedule.

The utilization of an extensive heating system allowed construction to continue despite temperatures falling below minus 40 degrees Celsius.

Suncor Millennium Naptha Unit & Hydrogen Plant
Suncor Millennium Naptha Unit & Hydrogen Plant : Projects : Bird Construction