The TransAlta Kent Hills Rehabilitation program involved the dismantling of 49 existing wind turbines, demolition of 50 foundations, replacing them with newly designed foundations and reassembling a combination of 50 V90 and V126 3.0MW wind turbines. As the prime contractor, Bird self-performed majority of the scope of work.
Our responsibilities included; crane pads, access road modification and maintenance, electrical de-energizing, collection installation, a lockout tagout program implementation, and essential testing of each wind turbine, foundation construction, foundation demolition and disposal, wind turbine generator dismantling and installing.
Client:
TransAlta Renewables Inc.
Contract Type:
Balance of Plant Engineering, Procurement & Construction
Project Size:
150 MW
Duration:
16 Months
Project Value:
Confidential