This project provides water service for a population of 133,000 and includes a new treated water reservoir that doubles existing capacity to 24,083 cubic metres (31,500 cubic yards).
Client:
Regional Municipality of Wood Buffalo
Consultant:
Associated Engineering
Contract Type:
Stipulated Sum
Duration:
28 months
Project Value:
$131,000,000

Bird’s work included:
- Ultraviolet building
- Transformer upgrade
- Plant waste management system
- Clearwell reservoir and high lift pumping station
- A five-storey operations building
- Filter clarification expansion and chemical distribution
Through careful planning and execution, Bird ensured the work within the existing water treatment plant did not disrupt the city’s drinking water supply.