Aerial view of a construction site next to a highway, featuring a large yellow crane, several excavators, construction materials, equipment, and fenced-off areas. Vehicles are visible on the adjacent roads.
Water & Environment, Water & Wastewater

MacKenzie Pumphouse and Reservoir Facility

The one-storey masonry block building was constructed utilizing sloped roof trusses and a veneer envelope. Perched above the 366-metre deep reservoir, Bird used a self-erecting crane to install the rigid and durable lattice form work girder, which allowed the walls and concrete roofing to be formed.

Client:
Regional Municipality of Wood Buffalo

Consultant:
AECOM

Contract Type:
Stipulated Sum

Project Size:
2,144 cu. m of concrete
(75,500 cu. yd of concrete)

Duration:
33 months

Project Value:
$18,400,000

A yellow bulldozer sits on bare soil in front of a large tan brick industrial building, with sunlight casting strong shadows across the scene.

The project required 2,144 cubic metres of concrete. With the majority of the concrete work completed during the winter months, extensive hoarding and heating was required. Bird also used a waterproofing additive in the concrete walls to increase the protection of the concrete from deterioration due to harsh environmental conditions.

Bird has been made aware of fraudulent vendor contracts targeting prospective and current suppliers. Please exercise caution and verify your contact before sharing payment information or accepting credit applications.