A large fault - a fracture in the rock resulting from earth movement - was detected on the upper portion of the exposed face, which could pose a risk to mining operations below. Consequently, approximately 40 million tons of material has to be removed from the wall to deal with the safety issue and to permit access to additional ore. The biggest challenge thus far has been HJO's ability to work within the blasting constraints and produce material that is sufficiently fractured and heaved to permit efficient excavation operations. Furthermore, different rock varieties have reacted differently to the drill and blast designs. By adjusting drilling patterns, powder factors and drill hole blasting sequence, the team has been able to achieve more efficient excavation operations.
Paul’s Peak Waste Rock Project
Project Overview
Project Gallery
Related Projects
BHP Jansen Fine Tailings
2Nations Bird Construction, a partnership between Beardy's and Okemasis Cree Nation, Fishing Lake Cree Nation and Bird Construction, completed the construction of a Fine Tailing system, and associated interceptor ditches.
View Project →
Artemis Gold Blackwater Mine
The Blackwater Gold Mine, developed by Artemis Gold Inc., is a greenfield gold mining and processing facility located in central British Columbia. The Blackwater Gold claim contains 334 million tonnes of gold resources, comprising both low-grade and high-grade ore.
View Project →
BHP Raw Ore & Product Storage Foundations
Bird is required to complete all forming, reinforcing steel, concrete pouring and finishing activities to complete the concrete foundations for the following main buildings at the BHP Jansen Stage 1 Project: Raw Ore Storage Building, South Crushing Building, Product Storage Building and the Product Loadout Building
View Project →
Residue Storage Area and Dams
Bird Heavy Civil Ltd. completed the residue storage area and dams project at Vale's Long Harbour Nickel Processing Plant, which included three earth-filled dams encapsulating the residue storage area.
View Project →
Voisey’s Bay Site Wide Concrete
The scope of work included the mill site building, coarse ore storage building, crusher, powerhouse, accommodation complex, site wide storage facility, and port site works.
View Project →
Fire Lake Mining
Since 2006, les Entreprises de Construction de Québec (LECQ), a division of Bird, has been continuously operating the Fire Lake iron ore mine for ArcelorMittal.
View Project →