Since 2019, Bird Construction has been an integral partner in the construction of the LNG Canada Project in Kitimat, BC, part of the largest energy investment in Canadian history. Bird’s involvement began with providing the initial clearing and civil work for the site, followed by the design-build of Cedar Valley Lodge, a 4,500-person workforce accommodation centre.

Client
JGC | Fluor BC LNG JV
Contract Type
Design-Build, Unit Price
Project Size
N/A
Duration
3 Years
Project Value
Confidential

As the project progressed, Bird provided the following additional services:

  • Design-Build of 16 non-process buildings
  • Terminal demolition
  • Effluent ponds
  • Process buildings and closure welding
  • OSBL and U-ditches