The Wuskwatim Generating Station project was comprised of the concrete supply and placement for the spillway, service bay, intake and powerhouse structures, as well as construction of the main dam and all remaining excavation required for the principal structures.

Client
Manitoba Hydro
Consultant
KGS Acres Ltd.
Contract Type
Unit Price
Project Size
106,273 cu. m of concrete
64,382 sq. m of formwork
7,500 tons of steel
Duration
46 months
Project Value
$400,000,000
Formwork Around Concrete Outflow Walls and Tower Crane against a Cloudy Sky

As a member of the project consortium, H.J. O'Connell, a division of Bird, provided world class construction services to the Wuskwatim Generating Station in concert with the utmost respect for the environment and the achievement of meaningful training and long-term benefits to the people of the area.