The Borealis Lodge Accommodation Complex is a 1,500-suite camp facility adjacent to a Suncor Energy Inc. oilsands development.
List Title :
Borealis Lodge
Page title :
Borealis Lodge Accommodation Complex
Detailed location :
FORT MCMURRAY, ALBERTA
Client :
Beaver Foods, a division of Cara Foods Ltd.
Consultant :
Barr Ryder Architects and Planners
Contract type :
Construction Management
Project value :
Undisclosed
Project size :
35,000 sq. m<br>(376,400 sq. ft)
Duration :
12 months
Award :
Lead certification level :
Featured :
No
Bird successfully managed 78 trade contractors within the rigid industrial plant safety and quality standards. The facility is comprised of 15 interconnected three-storey accommodation wings and a centralized core building complex with recreational facilities, kitchen, and a dining area capable of seating 1,000 occupants.
Built for permanent long-term use, the facilities are structural steel-framed on driven pile foundations with concrete floor slabs. The major challenge of the project was the complete design and construction through a short schedule and tight budget. All work was simultaneously designed and constructed along with a complete infrastructure that included roadways, utilities, a two-million litre water reservoir, and wastewater treatment plant.
[[Auto Insert Gallery here]]
Delivery Model :
Construction Management
Services :
- Pre-Construction/Early Contractor Involvement
Markets :
- Industrial Buildings
- Petrochemical
- Waste & Wastewater
- Workforce Housing
Location :
Alberta
Sector :
Oil and Gas