This facility provides storage for tooling, equipment, and components between MCR outages. The maintenance, refurbishment, and testing of equipment will also take place within the facility.
List Title :
Bruce Power Central Storage Facility
Page title :
Bruce Power Central Storage Facility
Detailed location :
Tiverton, Ontario
Client :
Bruce Power LP
Consultant :
Stantec Consulting Ltd.
Contract type :
Stipulated Sum
Project value :
$45,000,000
Project size :
10,220 sq. m <br>(110,000 sq. ft)
Duration :
16 months
Award :
Lead certification level :
Featured :
No
In preparation for the Major Component Replacement (MCR) outage program for the refurbishment of Bruce A and B Nuclear Generating Stations, a new 10,220 m2 Central Storage Facility (CSF) was constructed. This facility provides storage for tooling, equipment, and components between MCR outages. The maintenance, refurbishment, and testing of equipment will also take place within the facility.
Bird’s scope of work included the full site development, underground utilities, building erection, mechanical and electrical work, and the installation of the large overhead cranes to handle the materials in the facility. The project was completed in two phases, starting with the building construction, and then moving on to the interior fit-out and site service installations. The second phase of the project was on the critical path of Bruce Power’s MCR program and had an aggressive schedule to achieve substantial completion to enable the MCR work to proceed on schedule. Bird’s ISO 9001:2015 certification was a requirement for this project and added further value during the execution, ensuring that quality management standards were maintained at the highest level. This was the third contract awarded to Bird by this client, following the successful execution of the MCR Office Complex and MCR Storage Buildings projects.
[[Auto Insert Gallery here]]
Delivery Model :
General Contracting
Services :
- Pre-Construction/Early Contractor Involvement
Location :
Ontario
Sector :
Power