Skip to main content
logo-bird-white

Dorsey Converter Station

Feb 20, 2020, 03:53 AM
Manitoba Hydro's Dorsey Converter Station is the southern terminus for the utility's high voltage direct current transmission lines.
List Title : Dorsey Converter Station
Page title : Manitoba Hydro Dorsey Converter Station
Detailed location : WINNIPEG, MANITOBA
Client : MANITOBA HYDRO
Consultant : STANTEC INC.
Contract type : STIPULATED SUM
Project value : $5,100,000
Project size : 12,000 SQ. FT.
Duration : 18 MONTHS
Award :
Lead certification level :
Featured : No

Bird provided protection for the 5,000 square foot existing pre-engineered building by constructing a building to encase it. The construction consisted of cast-in-place foundation piles, which were required to support the 190 piece precast concrete structure that was loaded using a 500 ton crane.

The location of this project was particularly difficult since the Dorsey converter station is located inside of an operating Manitoba Hydro facility within close proximity to high voltage electrical lines. Bird’s team exercised extensive pre-planning and safety procedures to complete this job successfully and safely.

Delivery Model : General Contracting
Services :
Markets :
  • Process/Non-Process Buildings
Location : Manitoba
Sector : Power
Manitoba Hydro Dorsey Converter Station exterior under construction