Finning Facility Expansion

Feb 20, 2020, 03:54 AM
As the world's largest Caterpillar equipment dealer, Finning contracted Bird to complete an expansion to the existing repair shop, storage warehouse and two-storey office building at their Fort Nelson Finning location.
List Title : Finning Facility Expansion
Page title : Finning Facility Expansion
Detailed location : FORT NELSON, BRITISH COLUMBIA
Client : Finning (Canada)
Consultant : Robertson Kolbeins Teevan Gallaher Associates Ltd.
Contract type : STIPULATED SUM
Project value : $9,500,000
Project size : 2,700 sq. m.
Duration : 12 months
Award :
Lead certification level :
Featured : No

The scope of work for the Finning Fort Nelson facility included concrete foundations for the 2,700 square metre addition, metal cladding exterior, SBS roofing and site services.

At the onset of construction, the team was faced with a condensed schedule. Typically, foundation work is completed by early fall to allow construction to continue during the cold winter months. Due to budgeting adjustments prior to construction, Bird began the foundations in September with only one month to complete the work before the temperatures dropped in Fort Nelson. Bird presented cost savings to the owner including alternate metal cladding, aluminum feeders instead of copper, and ware plates a quarter-inch less thicker than originally specified.

In addition, the team was also challenged by the occupied site as the repair shop and the office remained operational during construction. As a result of Bird’s unwavering ability to successfully complete challenging projects, the Finning facility expansion was completed on time and on budget.

Delivery Model : General Contracting
Services :
Markets :
  • Warehouse
Location : British Columbia
Sector : Light Industrial