A series of residue ponds for the Inco Hydromet Demonstration Plant included site overburden stripping, pond excavation and berm construction and the installation of geomembrane liners in all of the ponds.
List Title :
Hydromet Plant Residue Ponds
Page title :
Inco Hydromet Plant Residue Ponds
Detailed location :
ARGENTIA, NEWFOUNDLAND AND LABRADOR
Client :
Inco Ltd.
Consultant :
SGE Hatch
Contract type :
Unit Price
Project value :
$2,600,000
Project size :
56,485 sq. m.<br> (60,800 sq. ft.)
Duration :
12 Months
Award :
Lead certification level :
Featured :
Yes
H.J. O'Connell, a division of Bird, constructed a series of residue ponds for the Inco Hydromet Demonstration Plant in Argentia, Newfoundland. The work consisted of site overburden stripping, pond excavation and berm construction and the installation of geomembrane liners in all of the ponds.
Project quantities included a total of 40,062 cubic meters of excavation, 911 meters of piping, over 56,485 square meters of geomembrane liner and 20992 square meters of geocomposite liner.
[[Auto Insert Gallery here]]
Delivery Model :
General Contracting
Location :
Newfoundland & Labrador
Sector :
Mining