Built into the side of a hill, the new two-storey Waverly Memorial School employed the use of retaining walls and tilt-up construction methods for the building envelope.
List Title : Waverly Memorial School
Page title : Waverly Memorial School
Detailed location : WAVERLEY, NOVA SCOTIA
Client : Department of Transportation & Infrastructure
Consultant : Harvey Architecture
Contract type : Design-Build
Project value : $7,300,000
Project size : 44,000 sq. ft
Duration : 12 months
Award :
Lead certification level : SILVER
Featured : No

The construction of the new Waverly Memorial School began with the demolition of two existing schools that were built in the mid 1900s. Built into the side of a hill, the new two-storey school employed the use of retaining walls and tilt-up construction methods for the building envelope.

With Bird’s firm schedule and keen organization skills, construction was expedited on time for the upcoming school year. Bird was able to fast-track the schedule by performing the demolition and construction of the new structure concurrently, which required extensive coordination between Bird and its subcontractors.

Delivery Model : Design-Build/Engineering, Procurement, Construction
Services :
  • LEED/Sustainable Construction
  • Pre-Construction/Early Contractor Involvement