Feb 20, 2020, 03:54 AM
Bird constructed the maintenance building and provided an expansion to the existing administration building at the MEG Energy Corporation oilsands plant.
List Title : MEG Energy Buildings
Page title : MEG Energy Maintenance and Administration Building
Detailed location : CONKLIN, ALBERTA
Client : MEG ENERGY CORPORATION
Consultant : RIDDELL KURCZABA ARCHITECTURE ENGINEERING INTERIOR DESIGN LTD.
Contract type : STIPULATED SUM
Project value : $10,000,000
Project size : 28,000 SQ. FT.
Duration : 9 MONTHS
Award :
Lead certification level :
Featured : No

MEG Energy Corporation currently has received approval to construct and operate the first two phases of the Christina Lake regional project on 23 of their 80 sections of leased oilsands land. The purpose of phase 2B is to increase the production capacity of the central processing facility to 60,000 barrels of bitumen per day. The phase 2B maintenance building is located immediately adjacent to the existing phase one and two processing facilities.

Bird constructed the pre-engineered 16,000 square foot maintenance building and provided an expansion to the existing administration building. The expansion includes modification to the existing walkway and the addition of two mudrooms.

Delivery Model : General Contracting
Services :
Markets :
  • Commercial
  • Petrochemical
  • Process/Non-Process Buildings
Location : Alberta
Sector : Oil and Gas
MEG Energy Maintenance and Administration Building exterior showing white, blue and grey cladding