Suncor Millennium Naptha and Hydro Plant

Feb 20, 2020, 03:53 AM
The Suncor Millennium Naptha Unit and Hydrogen Plant allows Suncor Energy to produce higher volumes of low-sulphur naphtha for further processing at their refineries.
List Title : Suncor Millennium Naptha and Hydro Plant
Page title : Suncor Millennium Naptha Unit and Hydrogen Plant
Detailed location : FORT MCMURRAY, ALBERTA
Client : North American Enterprises Ltd.
Consultant : Bantrel Co.
Contract type : Cost Plus
Project value : Undisclosed
Project size : 7,540 cu. m of concrete<br>(9,860 cu. yd)
Duration : 16 months
Award :
Lead certification level :
Featured : No

This large scale project required close coordination with other contractors to ensure safety and efficiency. Immediately following the completion of the foundation work, the mechanical contractors were quickly mobilized, setting equipment and erecting steel. Exposure to the harsh northern Alberta winter required the installation of protective hoardings to ensure the project remained on schedule.

The utilization of an extensive heating system allowed construction to continue despite temperatures falling below minus 40 degrees Celsius.

Delivery Model : General Contracting
Services :
Markets :
  • Civil
  • Petrochemical
Location : Alberta
Sector : Oil and Gas
Aerial view of Suncor Millennium Naptha Unit and Hydrogen Plant under construction Aerial view of construction at the Suncor Millennium Naptha Unit