The Syncrude UE-1 CC131 foundation for Syncrude's plant operations at the Fort McMurray oilsands facility represents a major expansion for Syncrude.
List Title : Syncrude UE-1 Upgrader Expansion
Page title : Syncrude UE-1 Upgrader Expansion
Detailed location : FORT MCMURRAY, ALBERTA
Client : Syncrude Canada LTD.
Consultant : Syncrude UE-1 Project
Contract type : Unit Price
Project value : $92,000,000
Project size : 34,405 cu. m<br>(45,000 cu. yd.)
Duration : 18 Months
Award :
Lead certification level :
Featured : No

As the general contractor for the construction of the civil work for plants 7-3, 8-3, 25-1,26-1, 19,21 and 32-2 on the UE-1 project, Bird completed the underground piping, excavation, backfill, electrical grounding and concrete foundations. The scope included over 34,400 cubic meters of concrete and 5,100 meters of underground piping along with considerable earthwork.

There were several concrete pours in excess of 1,500 cubic meters each. A large volume of concrete was placed during the winter months that required a considerable amount of winter heating and hoarding.

Delivery Model : General Contracting
Services :
Markets :
  • Civil
  • Petrochemical
Location : Alberta
Sector : Oil and Gas