Skip to main content
logo-bird-white

Vale Civil and Piling

Dec 17, 2020, 15:47 PM
The Vale SUB Civil project involved a substantial scope, including civil, concrete, electrical and instrumentation works. This project was to prepare for the eventual construction of a new powerhouse critical to the operation of the Smelter as the exiting powerhouse was deemed unsuitable for ongoing use.
List Title : Vale Civil and Piling
Page title : Vale Civil and Piling
Detailed location : COPPER CLIFF, ONTARIO
Client : Vale Canada Limited
Consultant : Undisclosed
Contract type : Lump Sum
Project value : $11,195,574
Project size : Undisclosed
Duration : 12 Months
Award :
Lead certification level :
Featured : No
The Vale SUB Civil project involved a substantial scope, including civil, concrete, electrical and instrumentation works. This project was to prepare for the eventual construction of a new powerhouse critical to the operation of the Smelter as the exiting powerhouse was deemed unsuitable for ongoing use. 

Major work included over 6,000 cubic metres of soil excavation to facilitate installation of 260 micropiles to bedrock, with an average depth of 80’ to bedrock. 5.5' micropile casings were employed in this particular application.

Some electrical grounding work was performed in concert with concrete installation to support future building and equipment requirements, as well as under slab drainage and buried services work (natural gas tie-ins, sanitary sewer piping, storm drainage, and a fire water main) to be tied into existing Vale systems. At project completion, approximately 2,000 cubic metres of concrete will be poured.          


Delivery Model : Industrial General Contracting
Services :
  • Self-Perform: Process
Markets :
  • Civil
  • Mine Infrastructure Development
  • Mining Support Services
Location : Ontario
Sector : Mining
exterior shot of vale complex displaying various structures and equipment exterior shot of site displaying equipment and structure